Current Month Activities


o Asphalt paving / expansion of parking lot
o Landscape plantings
o Plumbing fixtures
o Terrazzo floor installation
o Ceramic tile wall finishes.
o Finish trim (diffusers and grilles) of mechanical system.
o Acoustical ceiling tile installation.
o Interior storefront doors and system
o Folding door installation
o Acoustical wall panels
o Fire alarm and fire sprinkler finish trim.
o Installation of interior doors and hardware

 

Next Steps


o Punchlist completion
o Final completion and occupancy